Karun III Dam and Hydropower Plant

Client:
Iran Water and Power Development Co

Contractors:
Sabir, Farab, Tablier, GHORB

Location:    
28km east of Izeh in Khuzestan Province

 

Objectives:

1- Generate 4287 GWh/year electrical energy.
2- Flood Control.
3- Supply 1070 MCM water for agricultural uses

Dam & Power Plant Features:

Dam type

Double curvature concrete arch dam

Dam height

205 m

Crest length

462 m

Dam body volume

1.22 MCM

Reservoir volume

2970 MCM

Power plant installed capacity

8×250 MW

Construction Period

1994-2004

Foundation

Limestone

 